what you can do on the project
- time based -keeping on track -be on budget
- coordinating -materials -contractors -inspections
- Site Establishment -clear site of vegetation and rubbish, need to get to solid -top soil
- Site set out -profiles, string lines
- Foundation -ground plate (hilti nail gun), jack studs, braces
- Sub Floor/Floor -bearers, joist, insulation, fixings
- Wall Framing -erect frames, brace (temporary), plumb, straighten the frames, square diagonally. Fixings, straighten studs
- Roof Framing -trusses/braces, purlins, fascia,
- Exterior Cladding -Building wrap, cavity batterns, cladding material, windows and doors
- Interior Cladding -Insulation, plumbing, electrical, telephone, gas, tv cables, vacum, -Gib
- Finishing work -Interior door, kitchen, toilets, bathrooms, laundry, finishing trims, tiling
- Paint -drainlaying, driveway
- Dove tail joint
- Halving joint
- Bridle Joint
- Mitre halving joint
- Cross halving joint
- Stopped halving joint
- Hauched mortise and tenon joint
- Mortise and tenon joint
- Dove tail bridle joint